Middle High Auditorium
Fully Completed Project Date: June 2020
The Middle High School Auditorium is receiving upgrades below:
-
New Lighting
-
Front Projector
-
Back Short-Through Projector
-
New Projection screen
-
Carpet is being replaced only in aisle ways
-
Carpet is being removed in the front. Concrete will be epoxied
-
deteriorating sound proof panels removed from walls and replaced.
-
Although not part of the capital project, the district is looking to replace the stage curtains as they are deteriorating and ripping.
UPDATES:
-
This project has not commenced.
-
01/28/2020 - The auditorium at the MSHS is scheduled to receive the following upgrades during the first 3 days of the February break.
-
Long-throw and short-throw projectors​
-
2 new projections screens
-
upgraded sound system
-
-
05/21/2020 - Aisle carpet is installed and front landing will be painted with epoxy.​