MHS Secure Entrance
Fully Completed Project Date: January 2020



Receptionist Secure Entrance

The current design of the entrance makes it difficult for the receptionist to fully see the visitor coming to the door. There exists a large gap between the entrance and the receptionist. In this construction project, a secure entrance is being erected to vet incoming visitors and create a safer environment for all.
UPDATES:
-
11/08/19 This project has not commenced yet. However, it is scheduled to commence during the Christmas Holiday Break.
-
12/30/2019 - Front entrance reception area is currently in progress. Access is open. Expected delivery of specialized glass for doors and windows in March will render the job complete by April 3, 2020.
-
01/28/2020 - The canopy has been painted and "Every Student Every Day" lettering is up. Glass doors are still being constructed and scheduled for installation in April, 2020.
-
02/25/2020 - Doors and sliding glass for receptionist are installed.