Elementary Auditorium
Fully Completed Project Date: June 2020
The Cuba-Rushford Elementary Auditorium will receive some upgrades during the 2019-2020 school year. The upgrades consist of:
-
Replacing the carpeting
-
Adding speakers to increase sound
-
Adding a larger projection screen that encompases the stage
-
Placing a projector in the front and back of the auditorium.
​
​
-
UPDATES
-
08/06/2019 - This project has not begun yet
-
12/09/2019 - Elementary Auditorium projection systems & upgraded sounds systems (speakers) will be installed over Christmas break.
-
01/28/2020 - The auditorium at the elementary is scheduled to receive the following upgrades during February break.
-
Long-throw and short-throw projectors​
-
2 new projections screens
-
upgraded sound system - added speakers.
-
-
Testing of the screens ​​​and projectors will follow.
-
02/25/2020 - Projectors and screens have been installed. Additional speakers have been added and are installed. We are waiting for testing and training.​
-
5/21/2020 - Carpet has been removed. The Band Pit (which was covered) has been filled in. The carpet will be installed June 1st, 2020