Middle High Athletic Lockers & Weight Room

Fully Completed Project Date: March 2020

The district is looking to meet the needs of all of the students participating in physical education and all athletics programs by providing adequate spaces.  The new athletic locker rooms and upgrades to existing locker rooms provide:

  • Better supervision of students

  • Ability to secure students in an emergency situation

  • Ample stalls for changing

  • Running water

  • Access to more toilets and sinks

  •  Ability for all team to have a locker room

  • Instructional space for teams

UPDATES:

  • 05/10/19 - Commencing May 28, Kirst will be installing a fence on the white lines painted in the back parking lot.  The fence is being installed to keep students safe and to house materials and their equipment.

  • 07/12/19 - The foundation, plumbing, frost walls, and backfill are completed. Piles for both entrance canopies are in.  Piles for the long canopy entering the existing athletic area outside door are in.  Concrete flooring is scheduled to be poured starting the week of July 15th.

  • 07/30/19 Walls are going up.  How exciting!

  • 8/15/19 As the walls progress in construction, you can start seeing where the doors and windows will be.  Come check it out!  Sidewalks next to building and entrance into the weightroom are being poured.

    • Weight Room Update - The entrance door and the door into Mr. Tompkins have been cut out​.  Ceiling has been removed.

  • 09/04/19 - Middle Entrance by weight room outside door & Gym hallway door are now open for use.  Sidewalks near gym and middle entrance have been poured.  95% of outside block walls are complete!

  • 09/16/19 - Concrete floors are being poured on the 23rd of September with the roofing steal scheduled for arrival by the 30th of the same month. 

  • 09/30/19 - Floors are being poured.  Doors going into the pool and new hallway should be installed during the month of October. Steel scheduled to arrive end of October for roofing.

  • 11/08/19 - Walkway Canopies Steel in place.  Roof steel in place.  Decking will be installed the 8th of November.  Roofers are scheduled for Nov. 18th. 

  • 12/09/2019 -

    • Weight Room - The glass has been installed in the weight room entrance doors. New sounds system is currently being installed (with 6 speakers).

    • Athletic Locker - Canopy entrance and athletic building roofs are on.  Outer brick is completed. Interior block was should be finished this week.  Fireproofing between original building and new construction is taking place the start of December 24th, 2019.

  • 12/30/2019 - Fire proofing is currently being sprayed on the ceilings over the shower rooms and entrance ways adjacent to the pool walls.​

  • 01/28/2020 - Shower and restroom wall tile is up.  Skylights are installed. Rain-screen is going up as we speak.

  • 02/25/2020 - Locker rooms and bathrooms are 95% finished with lockers a fully installed.  bathroom fixtures are installed.  The outside rain screen is progressing.

  • 03/09/2020 - The final installations should be done this week.  Students will start taking their personal items out of the old locker rooms and moving in to new team rooms on March 23, 2020.

  • 05/21/2020 - Team Rooms are finished.  Sidewalks are installed.  Blacktop paving should be done the first week of June.

  • Existing Locker rooms are currently being renovated.

  • 6/11/2020 - In the old locker rooms, tile is complete.  Painting is finished.  Flooring will commence 6/15

Locker Bathrooms 2

Locker Bathrooms

MSHS Lockers

MSHS Lockers 2

MSHS Lockers 3

Athletic Facility2

Athletic Locker Sidewalks

Athletic Sidewalks

Athletic Sidewalks

Althletic Team Room Lockers

Athletic Facility3

Athletic Facility4

Athletic Facility5

Athletic Facility1

Athletic - Skylight

Athletic - Rain Screen2

Athletic - Rain screen

Athletic - Field Entrance

Athletic - Rain Screen 3

Athletic - Bathroom tile2

Athletic - Bathroom tile1

Athletic - Bathroom tile4

Athletic - Bathroom tile3

STEAM - HS 3

STEAM - HS 2

STEAM - HS

STEAM - HS 4

Athletic5

Athletic7

Athletic6

Athletic9

Athletic8

Athletic3

Athletic2

Athletic4

Weight Room6

Weight Room4

Weight Room3

Weight Room5

Weight Room

Canopy

Steel

Athletic5

Athletic4

Athletic6

Hallway Concrete poured

Concrete delivered to Locker Room #1

Concrete delivered to Locker Room #1

Pouring concrete

Prepping for concrete

Hallway from fields to locker rooms and gym

Pouring concrete

prepping for concrete

Vapor barrier in locker room #1

New Sidewalks

New Athletic Lockers

New Athletic Lockers

New Athletic Lockers

New Athletic Lockers

Weight Rm Foundation Block

Long Canopy Piles

Exit Entrance and Canopy Pile

Frost barrier going up.

Canopy Pile

Canopy Pile for entrance into gymnasium

2nd Exit foundation

2nd Exit foundation

New Athletic Lockers

Removing 2 trees and top soil

New Athletic Lockers

New Athletic Lockers

Line markings where fence will go up

New Athletic Lockers Location

New Athletic Lockers

© By CRCS

  • Facebook - Grey Circle
  • LinkedIn - Grey Circle
This site was designed with the
.com
website builder. Create your website today.
Start Now