Fully Completed Project Date: June 2020

STEM careers are growing 2.5 times faster than the non-STEM average in New York State, with those working in STEM careers earning almost twice the average for all workers in the State. Due to the rigor of STEM fields of study at the postsecondary level, it is critical to expose students to these areas early in their educational career. It is an economic imperative that New York students have the supports to master the skills they need to succeed.  

The district wants to provide hands on STEAM experiences that mirror current developing STEAM careers.  These include coding, computer science, robotics, science experiments, cross-curricular problem solving, etc.

  • The STEaM addition is an open concept hands on environment with opportunities for all styles of collaboration.

  • 2nd floor houses two new classrooms which will allow CRCS to provide all students their educational programing needed for them to be successful.  

UPDATES:

  • 08/10/19 - All foliage has been removed to allow for construction. 

  • 08/15/19 - Foundation has been dug.  Concrete footer forms are being installed.

  • 09/04/19 - Foundations are started.  Temporary Fire Escape is installed for emergencies only!

  • 09/16/19 - 1/2 of the foundation walls are in with egress available for emergency purposes.

  • 09/30/19 - The foundations are complete.  The are will be backfilled with gravel in preparation for starting the block wall.

  • 10/18/19 - Interior walls have started.  Exterior walls should be done by November 15th.

  • 11/08/19 - Ahead of schedule, exterior walls will be done by Nov. 11th.  Steel beam placement will commence within a couple of weeks.

  • 12/09/2019 - First floor is poured.  Weather permitting, the second floor concrete will be poured on Friday 13th.  

  • 12/30/2019 - Both 1st and 2nd floor completed.  Walls in 2nd floor have been installed.  Steal and decking for roof complete.

  • 01/28/2020 - Roof is partially done and electricians are currently working on the wiring.