Elementary Gymnasium - Track

Fully Completed Project Date: December 2020

The Cuba-Rushford Elementary Gymnasium will be upgraded to include an indoor track suspended above the gym floor.  The purpose of the track is two fold.  To provide opportunities for our older elementary students to walk, run and exercise, and to provide another area  for wellness outside of school hours for the Track & Field Team, the Cross Country Team, for community members and staff.

In addition to the track, the following items are being upgraded or adapted for ease of use and to provide equal access to all.​

  • Boys and Girls Bathrooms by the gym are becoming four individual family style bathrooms.

  • One of the family style bathrooms will open into the gym to provide better supervision of students during school hours.

  • Hallway doors near gym are being installed to safeguard other parts of the building when the gym is open to the community.

  • New Gym floor is being installed.

  • Scoreboards

  • Batting cage

  • 2nd Exit to outside track from both 1st and 2nd floor

  • Lift is being installed from the 1st floor to the track

UPDATES

  • 08/06/19 - This project has not begun.  It is scheduled to start in the spring of 2020.  However, you will see outside work being done this fall for egress purposes.

  • 09/04/19 - Outside the gym next to the outside track the foundation for the new fire escape will commence September 12, 2019.

  • 09/16/19 - Construction Meeting this morning - We are working outside the gym to create the foundation for the entrance and egress for the gym and 2nd floor track.  See photo

  • 09/30/19 - The week of October 7th, the concrete foundation is being poured.  Fence will come down after that and the area will be cleaned ready Spring 2020 construction.  APRIL 1, 2020 Interior and Exterior construction will Start.  Gym classes will be in Mr. Erickson's Office (Wink).

  • 10/18/19 - Pad is poured and fence is down.  Construction will begin APRIL 1, 2020

  • 5/21/2020 - Update

    • Gym floor removed​

    • Glue on floor was abaded - Air test came back with nothing detected.

    • Old Air handlers removed

    • Concrete floor cut and removed to fit the steal beams that support the track

    • Old bathrooms removed.

  • 6/11/2020​ - Beams are in.  The track is going in as we write.  Block walls are being erected for the hallway and gym bathrooms and inside stair tower.